top of page
  • Writer's pictureEm Chester

Windyway Dog Trust - New Cabin

We were asked to demolish the old site cabins at the Windyway Trust in Macclesfield and do the groudworks ahead of their new site cabin being installed.

The old cabin was removed from site, along with the asbestos following a site survey.

New foundations were excavated and 15 new pads were concreted to specifications provided by the Concept Cabins.

We installed new cable ducting for power and also new water mains, soil pipes and inspection chambers.

We delivered and laid aggregate to create a new base for the cabin to be installed and for tarmac around the new cabin, which was sourced through SRC.

Finally, we built a new concrete ramp and steps as well as installed a new DDA compliant handrail.


Thank you Windyway Trust, Mycocks concrete and W.T. Riley and Son's tarmac.






1 view0 comments

Recent Posts

See All
bottom of page